Basic Cost estimate for building permit and related services

1. TOPOGRAPHY COORDINATES & RECENT PHOTOS 

From 700€ to 1200€ for a plot of approximately 4.000m2   Estimated time  15-20 days

2. BUILDING PERMIT     

The cost  of the building permit in Greece is determined by the TECHNICAL CHAMBER OF GREECE.

For WandS construction projects the cost of the license varies from 90 €/m2 to 110€/ m2.  

For hotels and business units, the range starts from 100€/m2 and it can be 150€/m2.                                               

     2.1  Service for approvals requests

          1. Forest inspection                                                                          Minimum 2 months
          2. Archeology inspection                                                                  60 days
          3. Architectural Committee (In certain cases)                                45 to 90  days  (Average 2-3 months)
          4. Aviation Authority  / Port Authority etc. (In certain cases)        60 days
 

     2.2  Studies

          1. Architectural                                                                                  45-90 days  (Depending on the complexity)
          2. Static                                                                                                      Approximately 25  days
          3. Engineering / Energy Performance of Building Sector                        Approximately 25 days
          4. Energy efficiency
          5. Drainage
          6. Sewage
          7. Passive fire protection
          8. Heating
          9. Air conditioning
         10. Gas  (if necessary)
         11. Environmental Surroundings
         12. Time scheduling
 

     2.3  Supervision during the construction phase             

                                                   

     2.4  Tax charges

          1. VAT, according to stated agreement: 24%
          2. Engineers' Income Tax, TECHNICAL CHAMBER OF GREECE etc, according to the Technical Chamber Of Greece
 
 

3. OWNER INSURANCE CONTRIBUTIONS (Former IKA)  5-20€/m2

  

4. BUILDING INSPECTION

          1. During foundation                                                            Average cost 240€ per day plus traveling expenses
          2. Upon completion                                                               Average cost 240€ per day plus traveling expenses
 

5. CONNECTION WITH THE UTILITIES NETWORKS (ELECTRICITY, WATER, GAS)

          1. Energy construction certificate                                         Average cost 100€ / 5-15 days
          2. Plumbing installation certificate                                       Average cost 50€ / 5-15 days
          3. Electricity installation certificate                                       Average cost 50€ / 5-15 days
          4. Gas installation Certification / Examination                     Average cost 50-250 € / 15-60 days

 

Attention! The above requirements are indicative.